Back to the Intranet
         
Schedule Status:

*
`
*
BILL TO          
SHIP TO
FAT Type: FAT Date: Lease/Sale: Crate/Box:
Quote#: Quote Date: Video#: Ship Via:
ME Review: EE Review: Build By:  
Pymt Recvd: NDA: Order Rev.: Requested Ship:
  
Prod. Hrs Left: Prod. Hrs Total: Prod. Pct Done:    
Non Prod. Hrs Left: Non Prod. Hrs Total: Non Prod. Pct Done: Billed Pct Done:

Price (Gross):

Project Docs:




Discount:

Quote Docs:



Open in Explorer
Copy Path

Quantity Discount:


Commission:


Price (Net):

Customer Price:



Down Payment:
Prior to Ship Payment:
Final Payment:



 Down Pay Email
 Ship Pay Email
 Final Pay Email


✓ Wrike Down Pay
✓ Wrike Ship Pay
✓ Wrike Final Pay
★ Wrike Accounting Complete
Priority:    
Pay Comments:  Update Comments Don't Start Until:
Project Scope:
Notes:
Work Done:
 Representative:
Rep Commission(%):
 Tax Exempt(Y/N):
If exempt attach certificate of exemption:
 Tax ID:
Custom Brokers Name:
Custom Brokers Phone:
 Std Terms (55%,35%,10%):
Non Std Terms:

$56,985.00 $0.00 $0.00 $56,985.00
F1F2F3F4F5F6F7F8F9F10F11F12F13F14F15F16F17F18F19F20F21F22F23F24
Work Order #:2014185  Rev 0Prepared By:MARKNORDLINGDate Released:2014/09/18                  
F1F2F3F4F5F6F7F8F9F10F11F12F13F14F15F16F17F18F19F20F21F22F23F24
 BILL TO SHIP TO                    
AttnJames DunlopAttnJames Dunlop                    
Company:Universal WildeCompany:Universal Wilde                    
Address:201 Summer StreetAddress:201 Summer Street                    
                        
                        
City/State/Zip:Holliston, MA 01746  City/State/Zip:Holliston, MA 01746                      
Phone/Fax864-938-1704 Phone/Fax781-251-2700                     
Emailjeff.mcfadden@universalwilde.comEmailjeff.mcfadden@universalwilde.com                    


         
* To Refresh Totals - Click Save at Top *
EditXIDPart NumberSerial NumberPart NameCompleteTotal HoursHours RemainingQtyCostPriceDiscountCal PriceOn Hand
Edit2030591092211439-09106FEEDER DCC HCP 250 ED STD CONSet Complete8 Standard Production Build 8 hrs1 $16,195.00  0
Edit203067005200 SIGNAL LIGHT ASSY 250/350 45MMSet Complete2 Standard Production Build 2 hrs2 $410.00  0
Edit203074571500 PRESSURE ROLLER 250 FREE ROLLING WHEELSet Complete4 Standard Production Build 4 hrs2 $2,514.00  0
Edit203087013100 START SENSOR DIFFUSE REFLECT - ML12Set Complete2 Standard Production Build 2 hrs2 $642.00  1
Edit203094303100 CONV STRADDLE MNT 8020 550Set Complete6 Standard Production Build 0 Integration and Testing 6 hrs2 $1,242.00  0
Edit203109279400 ACCUTIPPING W/ENCODERSet Complete8 Integration and Testing 8 hrs2 $4,995.00  1
Edit203129290500 DCC IP STANDARD SPARE PARTS KITSet Complete1 Pre-Production 1 hrs1 $1,260.00  8
Edit203137013400 LOW PROD SENSOR 2" DIFFUSE - MLV17Set Complete2 Standard Production Build 2 hrs2 $372.00  8
Edit20314  INSTALLATION AND INTEGRATION $ 995.00 PER DAYSet Complete 0 hrs1 $2,985.00   
Edit2041791092211439-09107MFT 250 HCP DCC ED STD CONFSet Complete8 Standard Production Build 8 hrs1 $16,195.00  0
+ denotes that software settings are available for this piece of equipment.

Labor Hours
* To Refresh Totals - Click Save at Top *


   



Purchase orders for this Work Order
EditXIDDescriptionPOPartialCost
Edit2270MIDWEST CRATING - 64" L X 42" W X 26" H ID,21902yes($236.00)