Back to the Intranet
         
Schedule Status:

*
`
*
BILL TO          
SHIP TO
FAT Type: FAT Date: Lease/Sale: Crate/Box:
Quote#: Quote Date: Video#: Ship Via:
ME Review: EE Review: Build By:  
Pymt Recvd: NDA: Order Rev.: Requested Ship:
  
Prod. Hrs Left: Prod. Hrs Total: Prod. Pct Done:    
Non Prod. Hrs Left: Non Prod. Hrs Total: Non Prod. Pct Done: Billed Pct Done:

Price (Gross):

Project Docs:



Open in Explorer

Discount:

Quote Docs:



Open in Explorer
Copy Path

Quantity Discount:


Commission:


Price (Net):

Customer Price:



Down Payment:
Prior to Ship Payment:
Final Payment:



 Down Pay Email
 Ship Pay Email
 Final Pay Email


✓ Wrike Down Pay
✓ Wrike Ship Pay
✓ Wrike Final Pay
★ Wrike Accounting Complete
Priority:    
Pay Comments:  Update Comments Don't Start Until:
Project Scope:
Notes:
Work Done:
 Representative:
Rep Commission(%):
 Tax Exempt(Y/N):
If exempt attach certificate of exemption:
 Tax ID:
Custom Brokers Name:
Custom Brokers Phone:
 Std Terms (55%,35%,10%):
Non Std Terms:

$112,122.00 $0.00 $30,346.00 $81,776.00
F1F2F3F4F5F6F7F8F9F10F11F12F13F14F15F16F17F18F19F20F21F22F23F24
Work Order #:2019170  Rev 0Prepared By:JIMILERDate Released:2019/11/08                  
F1F2F3F4F5F6F7F8F9F10F11F12F13F14F15F16F17F18F19F20F21F22F23F24
 BILL TO SHIP TO                    
AttnSatoshi FukanumaAttnSatoshi Fukanuma                    
Company:Iwai Tsusho K.K. - 6 FeedersCompany:Iwai Tsusho K.K. - 6 Feeders                    
Address:4-6, 5-Chrome, Nishi-Nippori, Arakawa-kuAddress:4-6, 5-Chrome, Nishi-Nippori, Arakawa-ku                    
                        
                        
City/State/Zip:Tokyo,  116-0013  JapanCity/State/Zip:Tokyo,  116-0013  Japan                    
Phone/Fax+81 3 5810 6361 Phone/Fax+81 3 5810 6361                     
Email Email                     


         
* To Refresh Totals - Click Save at Top *
EditXIDPart NumberSerial NumberPart NameCompleteTotal HoursHours RemainingQtyCostPriceDiscountCal PriceOn Hand
Edit4196391084321948-10030FEEDER 350 XED IP3 JMTR STD CFGSet Complete4 Integration and Testing 1 Shipping 13 Standard Production Build 1 Pre-Production 19 hrs1 $16,879.000.00$16,879.002
Edit419647176000 CBL 12/26 AWG M12 M 3M ASSYSet Complete6 Standard Production Build 6 hrs6 $204.00  7
Edit41965  PRODUCT SUPPORT ROD SPACERSet Complete 0 hrs6 $65.00   
Edit4224391084321948-10031FEEDER 350 XED IP3 JMTR STD CFGSet Complete4 Integration and Testing 1 Shipping 13 Standard Production Build 1 Pre-Production 19 hrs1 $16,879.000.00$16,879.002
Edit4224491084321948-10032FEEDER 350 XED IP3 JMTR STD CFGSet Complete4 Integration and Testing 1 Shipping 13 Standard Production Build 1 Pre-Production 19 hrs1 $16,879.000.00$16,879.002
Edit4224591084321948-10033FEEDER 350 XED IP3 JMTR STD CFGSet Complete4 Integration and Testing 1 Shipping 13 Standard Production Build 1 Pre-Production 19 hrs1 $16,879.000.00$16,879.002
Edit4224691084321948-10034FEEDER 350 XED IP3 JMTR STD CFGSet Complete4 Integration and Testing 1 Shipping 13 Standard Production Build 1 Pre-Production 19 hrs1 $16,879.000.00$16,879.002
Edit4224791084321948-10035FEEDER 350 XED IP3 JMTR STD CFGSet Complete4 Integration and Testing 1 Shipping 13 Standard Production Build 1 Pre-Production 19 hrs1 $16,879.000.00$16,879.002
Edit427125312400 SENSOR ULTRASONIC DBL DETECTSet Complete 0 hrs6 $1,477.000.00$8,862.001
Edit427132012540 DBL DETECT SENSOR MOUNTSet Complete 0 hrs6 $62.000.00$372.002
+ denotes that software settings are available for this piece of equipment.

Labor Hours
* To Refresh Totals - Click Save at Top *
 DepartmentQuoted HoursEst. HoursHours RemainingBilled HoursxidStart DateResource(s) AssignedAssignmentHistory
EditMechanical Eng. 0 0 005347
EditElectrical Eng. 0 0 005348
EditSoftware Eng. 0 0 005349
EditIntegration 64 64 5955350
EditMachine Shop 0 0 -28285351
EditManagement 0 0 005352
EditProduction 78 78 24.7553.255353
EditEE Technician 0 0 005354


   



Purchase orders for this Work Order
EditXIDDescriptionPOPartialCost
Edit4683MIDWEST CRATING - 86"L X 40"W X 52"H ID33978yes($348.00)