Back to the Intranet Home Page Lead Time Item List Lookup
Add New Lead Time Item     Return to Lookup Tables    
Edit ID Traveler Status Description Identifier Weight Minimum Notes
Edit 1 120 - MECHANICAL ENGINEERING 10 - Review order ENGINEERING-ORDER-REVIEW 1 1 time spent reviewing the order with sales
Edit 2 120 - MECHANICAL ENGINEERING 20 - Create a drawing ENGINEERING-DRAWING 5 0 time spent creating each drawing
Edit 3 120 - MECHANICAL ENGINEERING 30 - Engineering hours divided by 8 ENGINEERING-HRS 8 0 engineering days of work
Edit 5 130 - PROCUREMENT 10 - Create job ticket MATERIALS-CREATE-JOB-TICKET 1 1 time spent creating the job ticket
Edit 6 130 - PROCUREMENT 20 - Order custom parts MATERIALS-ORDER-CUSTOM-PARTS 5 0 ordering custom parts from external vendors
Edit 7 130 - PROCUREMENT 30 - MFT machine shop MATERIALS-MFT-MACHINE-SHOP 5 0 ordering custom parts from MFT machine shop
Edit 15 130 - PROCUREMENT 40 - External machine shop MATERIALS-EXTERNAL-MACHINE-SHOP 30 0
Edit 8 140 - PRODUCTION 10 - Production hours divided by 8 PRODUCTION-HRS 8 0 production days of work
Edit 12 170 - QA 10 - QA on machines QA 1 1 QA per machine
Edit 13 180 - SHIPPING 10 - Shipping for machines SHIPPING 1 1 Shipping per machine
Edit 9 190 - REDLINE LOG NOT COMPLETE 10 - Each APL add 1 day INTEGRATION-APL 1 0 APL integration
Edit 4 190 - REDLINE LOG NOT COMPLETE 10 - Review order INTEGRATION-ORDER-REVIEW 0.25 0.25 time spent reviewing the order
Edit 10 190 - REDLINE LOG NOT COMPLETE 20 - Each conveyor add 3 weeks INTEGRATION-CONVEYOR 15 0 Conveyor integration
Edit 11 190 - REDLINE LOG NOT COMPLETE 30 - Integration hours divided by 8 INTEGRATION-HRS 8 0 integration days of work